Treasury Liquidity Release Q3
Target go-live: Jun 11, 2026 (T-30 days) · Implementation: 2026-06-11 22:00 – 2026-06-12 04:00 UTC
Plain-English explanation: Score is 79 because test execution is 84% complete, pass rate is 89%, 4 High defect(s) remain open, Operations sign-off is pending, 1 vendor confirmation pending, and 1 required pre-go-live checklist item incomplete.
Score Breakdown Panel
Every factor's weight, raw score, weighted contribution, and status — the calculation behind today's readiness number.
| Factor | Weight | Raw score | Contribution | Status | Notes |
|---|---|---|---|---|---|
| Requirements coverage | 12% | 78% | 9.4 | Yellow | 31 of 35 requirements have test coverage (89%). 1 critical requirement(s) without coverage; 1 missing acceptance criteria. |
| Test execution completion | 13% | 84% | 10.9 | Yellow | 101 of 120 test cases executed (84%). |
| Test pass rate | 12% | 89% | 10.7 | Yellow | 80 of 90 executed tests passed (89%). |
| Open Critical / High defects | 18% | 69% | 12.4 | Orange | 0 open Critical, 4 open High, 8 open Medium defects. 3 aged beyond 14 days. |
| Change scope risk | 10% | 89% | 8.9 | Yellow | 0 high-impact change(s) without rollback plan; 1 CAB approval(s) pending; 1 conditional CAB; 1 customer-facing change(s) missing release notes. |
| Pre-go-live checklist completion | 8% | 77% | 6.2 | Yellow | 11/15 required items complete, 1 waived (with justification), 3 still open. |
| Risk register / residual risk | 7% | 64% | 4.5 | Orange | 9 open risk(s) — 1 High/Critical residual, 6 Medium residual. |
| Blocked dependencies | 7% | 70% | 4.9 | Orange | 1 blocked dependency(ies) (1 Critical). 0 overdue. |
| Environment readiness | 5% | 96% | 4.8 | Green | 6 environment(s) tracked. 0 Red, 1 Yellow. |
| Business sign-off | 4% | 84% | 3.4 | Yellow | 6/8 approved; 1 conditional; 0 rejected. |
| Approval workflow completion | 2% | 57% | 1.1 | Red | 5/10 approved; 1 conditional; 0 rejected. |
| Vendor readiness | 1% | 75% | 0.8 | Yellow | 3/4 vendor(s) confirmed. 0 blocked, 0 at risk. |
| Data quality confidence | 1% | 84% | 0.8 | Yellow | Avg upload quality 88%. 2 error-class issue(s). |
| Total | 100% | 79 | Medium / High |
Change scope summary
Change tickets
8
Regulatory-impacting
6
High/Critical impact
3
Missing rollback
0
Top risks (from formal risk register)
- 1
Regulatory feed dependency blocked
Residual High · Owner: Faye Ng · Secondary submission channel; daily regulator engagement; escalation owner named.
- 2
Four high-severity defects remain open
Residual Medium · Owner: Marcus Doyle · Daily defect triage; targeted retest sweep on Day -3.
- 3
Vendor NovaFeed confirmation pending
Residual Medium · Owner: Helen Asare · Escalate via Account Director; backup vendor identified for emergency rerouting.
- 4
Downstream reporting feed change missing regression evidence
Residual Medium · Owner: Diego Lopez · Targeted downstream regression sweep + CAB approval evidence to be attached before Final Go/No-Go.
- 5
UAT environment Yellow due to data refresh delay
Residual Medium · Owner: Marcus Doyle · Tactical synthetic dataset used; refresh expected within 3 days.
- 6
Operations sign-off outstanding
Residual Medium · Owner: Renata Silva · Daily PMO escalation; staffing plan finalized by Day -7.
System risk heatmap
Tracking nominal
Score 82
Tracking nominal
Score 91
Blocked: DEP-001
Score 68
Tracking nominal
Score 91
Blocked: DEP-001
Score 68
Tracking nominal
Score 82
1 high/critical defect(s) open
Score 83
1 high/critical defect(s) open
Score 83
Defect summary
Open Critical
0
Open High
4
Open Medium
9
Closed
11
Approval chain status
Pre-go-live checklist
- Rollback tested in UAT — Marcus DoyleComplete
- Rollback plan approved — Renata SilvaComplete
- DBA sign-off for schema changes — Owen PatelComplete
- Operations team briefed — Renata SilvaComplete
- Production support team staffed for first 48 hours — Renata SilvaIn Progress
- Runbook published — Marcus DoyleComplete
- Smoke test plan confirmed — Marcus DoyleComplete
- Production validation owner assigned — Priya RaghavanComplete
- Release notes published to customers — Hannah LiuIncomplete
- CAB approval received — Karen MwangiComplete
- Business communication sent to stakeholders — Helen AsareComplete
- Monitoring alerts configured — Owen PatelComplete
- Vendor readiness confirmed — Helen AsareIn Progress
- Compliance sign-off completed — Karen MwangiComplete
- Test data refresh completed in UAT — Marcus DoyleWaived
Stakeholder communication summary
May 12, 2026, 8:00 AM · Email · Helen Asare
Go/No-Go meeting — pre-read — Distributed Release Health Card and AI executive summary as pre-read.
May 11, 2026, 5:00 PM · Slack · Faye Ng
Regulator handshake — Day +1 update — Regulator acknowledged secondary submission channel and confirmed Day +1 submission slot.
May 11, 2026, 1:00 PM · Executive Update · Helen Asare
Treasury Liquidity Q3 — Conditional Go memo — Memo recommending Conditional Go pending Operations sign-off, NovaFeed confirmation, and CHG-2026-1004 rollback plan.
May 10, 2026, 9:00 AM · Steering Committee Update · Helen Asare
Treasury Liquidity Q3 — readiness update — Communicated current 78% readiness, top 4 risks, NovaFeed confirmation timeline, Operations sign-off plan.
May 9, 2026, 4:00 PM · Email · Marcus Doyle
DEF-1042 retest pass — submission feed delay resolved — Retest confirmed feed delay resolved at 1.2M record scenarios.
May 8, 2026, 11:00 AM · Status Report · Helen Asare
Weekly release status — Week 4 — Score 74 → 78 over the week. Top blockers: Ops sign-off, vendor confirmation, four high defects.
AI evidence and assumptions
Evidence
- Test execution: 84%
- Pass rate: 89%
- Approval completion: 5/10
- Pre-go-live checklist: 11/15
- Data quality: 85%
Risk drivers
- DEP-001: Downstream regulator feed for LCR daily submission. (Critical)
- Operations business sign-off pending
- 4 High-severity defects open
- Vendor confirmation pending: NovaFeed
- Required checklist item incomplete: Release notes published to customers
- UAT-Treasury environment Yellow: Test data refresh delayed for Basel III stress scenarios; remediation in progress.
Assumptions
- Waived items remain valid until resolved
- CAB conditional approval conditions assumed met before final Go/No-Go
- Vendor maintenance window paused for cutover
- Performance fix for DEF-1046 shipping in next build
Human override history
No human overrides recorded for this release. Override events would appear here with original recommendation, original score, override reason, user name, role, and timestamp.
Recommended actions before Go/No-Go
- Obtain Operations sign-off and confirm hypercare staffing
- Retest or formally accept remaining high defects (DEF-1041, DEF-1042, DEF-1043, DEF-1045)
- Secure written confirmation from NovaFeed
- Complete required checklist item(s): Release notes published to customers
- Resolve or mitigate blocked dependency: Downstream regulator feed for LCR daily submission.
- Return UAT-Treasury environment to Green
Audit trail summary, shareable read-only link, and PDF / PPTX / CSV / Excel exports available via the action buttons above.